Construction Loan Cost Calculator
Updated November 19, 2026
Enter your build figures
How is the cost of a build worked out?
Total cost = land + build budget + soft costs + contingency + closing costs + loan points + interest + holding costs + selling costs
Contingency = build budget × contingency %. Interest = loan amount × annual rate ÷ 12 × (months to build × average drawn share + months to sell). Points = loan amount × points %. Cash you bring = total cost, without selling costs, minus the loan. Profit = value when finished − total cost.
Worked example
Suppose you buy a lot for $150,000, plan a $400,000 build with $30,000 of soft costs and a 5% contingency, and expect the home to be worth $800,000 when it is finished. A $480,000 loan at an example rate of 11% with 2 points, half drawn on average over a 10-month build and fully drawn for the 3 months it takes to sell, with $8,000 of closing costs, $600 a month to hold and 6% selling costs, gives this estimate.
- Project cost
- $600,000
- Loan interest
- $35,200
- Total cost
- $708,600
- Cash you bring
- $180,600
- Profit: $800,000 − total cost
- $91,400
Construction calculator questions
What goes in the build budget and soft costs?
The build budget is the hard cost of construction: site work, foundation, framing, systems and finishes, usually from your builder's line-item budget. Soft costs are the rest of the work to get there: plans, engineering, permits, impact fees and inspections. Lenders review both against the plans before closing.
Why is interest worked out on the drawn balance?
Construction loans pay out the build money in draws as the work is inspected, so you pay interest only on what has been drawn. The average drawn share lets you model that: if the loan is drawn evenly over the build, about half of it is out on average. Leave it blank to charge interest on the whole loan, the higher and safer estimate.
What is the cash I bring?
It is the money you put in before the home sells or refinances: the total cost, without selling costs, minus the loan. It includes the land equity, any part of the budget the loan does not cover, closing costs, points, interest and holding costs.
Is this a loan quote?
No. It is an estimate from your own figures. A ground-up construction loan is sized on the project cost and the value once it is finished, and the leverage, rate, points and draw schedule are confirmed for each deal through underwriting.